KAMPALA
More than one million people in Wakiso, Mpigi, Kampala and Entebbe are expected to benefit from improved water supply and sanitation services under a €145m (about Shs600b) project.
The Wakiso West Water and Sanitation Project, led by the Government and the National Water and Sewerage Corporation (NWSC), will include the construction of a water treatment plant at Bwerenga, on the shores of Lake Victoria, with a daily capacity of 62,500 cubic metres.
NWSC managing director Dr Silver Mugisha said the investment would address growing demand for safe water and sanitation in rapidly urbanising communities.
“We want to ensure that communities in these rapidly growing areas have access to reliable and safe water, while also addressing the sanitation challenges that threaten public health and the environment,” he said.
On Tuesday, NWSC signed a consultancy contract worth €9.48m and Shs2.15b with NIRAS A/S, in a joint venture with Fichtner GmbH & Co. KG, to support the project’s implementation.
The project will cover Kiringente, Mpigi, Kajjansi, Kasanje, Kyengera and Wakiso, among other surrounding communities.
Infrastructure will include five reservoirs with a combined storage capacity exceeding 15,250 cubic metres, pumping stations and water transmission and distribution networks.
NWSC also plans to establish 941 community water dispensers, targeting underserved communities, including informal settlements where about 160,000 people are expected to benefit.
The project will also include a faecal sludge treatment plant at Kajjansi, capable of processing at least 400 cubic metres daily.
The consultancy will involve 20 months of design preparation, followed by construction supervision and commissioning.