Do Uganda’s Stadium Projects Reflect the Billions Invested?

Do Uganda’s Stadium Projects Reflect the Billions Invested?

November 19, 2026
British-Ugandan returns to Entebbe childhood home after nearly 60 years

British-Ugandan returns to Entebbe childhood home after nearly 60 years

November 19, 2026
Mao admits JLOS credibility at stake as Uganda prepares for Justice Week

Mao admits JLOS credibility at stake as Uganda prepares for Justice Week

November 19, 2026
VINAStech Advert
Museveni, Samia Hold Talks at State House Entebbe, Agree to Fast-Track EACOP and SGR

Museveni, Samia Hold Talks at State House Entebbe, Agree to Fast-Track EACOP and SGR

November 18, 2026
Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

November 18, 2026

Rooney reveals he contemplated suicide during Manchester United career

November 17, 2026
Kampala, Wakiso to get 3.3 million mosquito nets in final distribution wave

Kampala, Wakiso to get 3.3 million mosquito nets in final distribution wave

November 17, 2026
Amuriat: We are ready for Kikuube By-election

FDC sets conditions for national dialogue

November 17, 2026

16 Days of Activism: A Call to Confront Rape and Domestic Violence in Wakiso

November 17, 2026
Teacher shortage stretches government schools within and around Kampala

Teacher shortage stretches government schools within and around Kampala

November 17, 2026

From Campus to Content Creation: Makerere student turns passion into a way to pay tuition

November 17, 2026
Young African leaders urged to turn Pan-Africanism into action at UBUMWE Summit 2026

Young African leaders urged to turn Pan-Africanism into action at UBUMWE Summit 2026

November 17, 2026

Police officer, teacher remanded over forged UNEB letters

November 16, 2026
  • About Us
  • Internship
  • Contact Us
Thursday, November 19, 2026
Parrots Media
No Result
View All Result
  • Login
  • News
    Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

    Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

    Amuriat: We are ready for Kikuube By-election

    FDC sets conditions for national dialogue

    16 Days of Activism: A Call to Confront Rape and Domestic Violence in Wakiso

    Police officer, teacher remanded over forged UNEB letters

    Move beyond account ownership, BOU tells banks

    Move beyond account ownership, BOU tells banks

    Before changing jobs, read the fine print

    Before changing jobs, read the fine print

    Trending Tags

  • Climate Change
  • Business
  • Science and Technology
  • Sports and Entertainment
  • Business
  • Others
    • Education
    • Lifestyle
    • Religion
    • Opinions
  • News
    Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

    Vandalism of King of Tooro Poster in Kyegegwa Sparks Outrage

    Amuriat: We are ready for Kikuube By-election

    FDC sets conditions for national dialogue

    16 Days of Activism: A Call to Confront Rape and Domestic Violence in Wakiso

    Police officer, teacher remanded over forged UNEB letters

    Move beyond account ownership, BOU tells banks

    Move beyond account ownership, BOU tells banks

    Before changing jobs, read the fine print

    Before changing jobs, read the fine print

    Trending Tags

  • Climate Change
  • Business
  • Science and Technology
  • Sports and Entertainment
  • Business
  • Others
    • Education
    • Lifestyle
    • Religion
    • Opinions
No Result
View All Result
Parrots Media
No Result
View All Result
Home Entertainment Sports

Do Uganda’s Stadium Projects Reflect the Billions Invested?

Isaac Akugizibwe by Isaac Akugizibwe
November 19, 2026
in Sports
0
Do Uganda’s Stadium Projects Reflect the Billions Invested?
128
SHARES
526
VIEWS
Share on FacebookShare on X

By Sekitto Reagan,

KAMPALA

READ ALSO

Rooney reveals he contemplated suicide during Manchester United career

Manchester United pursue Pochettino as Palace dismiss Sage

As Uganda prepares to co-host the Africa Cup of Nations alongside Kenya and Tanzania, questions emerge over the cost, construction progress and accountability of public funds invested in Akii-Bua and Mandela National Stadium.
Uganda’s preparations to co-host the 2027 Africa Cup of Nations are increasingly taking shape, with major investments being directed towards sports infrastructure. From the construction of Akii-Bua Olympic Stadium in Lira to the remodelling of Mandela National Stadium in Namboole, government has committed billions of shillings to ensure the country meets international football standards.

However, beyond the impressive structures and construction progress being reported, a bigger public affairs question is emerging: does the physical progress and quality of these stadium projects reflect the enormous amounts of public money allocated to them?
With AFCON 2027 scheduled to kick off on June 19, 2027, Uganda has a limited period to complete the required infrastructure. But questions surrounding funding releases, project costs, construction timelines and value for money are increasingly attracting attention from accountability institutions and Parliament.

One of the biggest investments is Akii-Bua Olympic Stadium in Lira City, named after Uganda’s legendary Olympic gold medallist John Akii-Bua.
According to the Public Procurement and Disposal of Public Assets Authority (PPDA) September 2026 project inspection report, government, through the National Council of Sports (NCS), signed a contract with Egyptian construction company SAMCO National Construction Company on December 6, 2024, worth US$129.743 million, approximately Shs470 billion.
The 20-month contract provides for a 20,000-seater stadium with an athletics track, a 2,000-seat indoor arena, a semi-Olympic swimming pool, training facilities, outdoor courts, parking space for 1,000 vehicles, a hostel and other supporting infrastructure.
The financing arrangement was designed around a 50-50 cost-sharing model, with government and the contractor each expected to contribute US$64.87 million. Government is expected to reimburse the contractor’s contribution upon completion and handover of the project.
While the project represents a significant investment in sports infrastructure in northern Uganda, the PPDA inspection raised concerns about funding and construction management.

The report established that NCS budgeted Shs241 billion for Akii-Bua during the financial years 2024/25 and 2025/26 but received approximately Shs144.65 billion, representing about 60 per cent of the planned allocation.
The authority also established that the advance payment of US$26.67 million, which was required within 28 days of signing the contract, was only made on April 10, 2025, approximately four months after the agreement was signed.
This delayed the contractor’s mobilisation and commencement of construction.

By June 2026, PPDA reported physical progress at 63 per cent against time progress of 68.3 per cent, indicating that construction was slightly behind schedule. It also noted that delayed payments and complex foundation works contributed to the slow progress.
However, subsequent developments showed improvement. According to Daily Monitor reporting on September 23, 2026, Akii-Bua had reached 83 per cent physical completion and 87 per cent financial progress.
A later report published on October 28 placed construction progress at 85 per cent, with handover scheduled for January 2, 2027.
This improvement offers encouragement, although the difference between physical and financial progress deserves further scrutiny. What exactly accounts for the financial progress being higher than the completed physical works, and how is government ensuring that the remaining construction delivers the quality promised under the contract.

At Mandela National Stadium, Namboole, the accountability questions take a different dimension.
The facility is undergoing its second phase of remodelling to meet Confederation of African Football (CAF) and FIFA requirements ahead of AFCON 2027.

According to Daily Monitor reporting published on February 26, 2026, the second phase of renovation was valued at approximately Shs248 billion, following an earlier renovation phase that cost Shs97 billion. This brings the two phases to approximately Shs345 billion.
The UPDF Engineering Brigade is undertaking the works under an arrangement involving the Ministry of Education and Sports and the Ministry of Defence and Veteran Affairs.
The renovation is intended to increase the stadium’s seating capacity from approximately 38,268 to 45,000 spectators, while improving dressing rooms, VIP and VVIP facilities, media infrastructure, spectator areas, medical facilities and the playing surface.

However, the project has also attracted questions about additional expenditure. During parliamentary inspections in October 2026, officials disclosed that an additional Shs38 billion had been requested to address inflation and fluctuations in foreign exchange rates.
National Council of Sports chairman Ambrose Tashobya indicated that the additional funding was subject to verification before approval and expenditure.
The figures presented during the October 2026 parliamentary inspection also provide an important picture of the project’s financial position.
According to New Vision, the UPDF Engineering Brigade reported that it had received approximately Shs220 billion and spent Shs123 billion, while physical construction progress stood at 51 per cent.
This means that although substantial resources had been released to the project, a significant portion of the received funds had not yet been reflected in completed physical works.
Officials explained that some of the money was committed to activities yet to be executed. This distinction is important because money received, money committed and money actually spent are different financial measures.
Nevertheless, Parliament has a responsibility to establish how the expenditure corresponds with the completed work and whether the additional funding request is adequately justified.

Beyond the two stadiums, a wider government infrastructure programme raises further questions about planning and financial management.
In its September 2026 inspection report, PPDA revealed that the National Council of Sports had budgeted Shs863.267 billion cumulatively for Hoima City Stadium, Akii-Bua Olympic Stadium and Kyambogo University Training Facility between FY2023/24 and FY2025/26.
However, only Shs563.998 billion had been released, representing 65.3 per cent of the planned funding.
The funding gap was particularly significant in FY2025/26, when government released only Shs128.971 billion out of a budgeted Shs426.973 billion, representing approximately 30 per cent.
The report further established that by June 2026, only one of the 17 planned project deliverables under the wider Sports Infrastructure Development Project had been fully completed, despite approximately 40 per cent of the five-year implementation period having elapsed.
Six deliverables had not yet commenced, while 10 were under implementation.
The authority also raised concerns about project scope changes, delayed completion of appraisal processes and the slow implementation of training facilities required for AFCON 2027.
These findings are particularly important because hosting a successful tournament requires more than two impressive stadiums. Participating teams need properly equipped training grounds, accommodation arrangements, medical facilities and other supporting infrastructure.
PPDA specifically recommended that government fast-track the delayed training facilities and develop time-bound recovery plans to ensure they are completed, tested and certified before the tournament.
Government has maintained that Uganda is making progress towards meeting its hosting obligations.

In  September 2, 2026 update, the Government Citizen Interaction Centre, communicating the position of the AFCON 2027 Local Organising Committee, reported that Akii-Bua was approaching 80 per cent completion and that the country remained on course to have its three main stadiums ready by December 2026.
The committee also reported that government had provided Shs135.7 billion for nine additional training facilities.
These developments demonstrate that infrastructure preparation is ongoing, although the different progress figures reported at different dates underline the importance of regular, independently verified updates.
The bigger question, however, is whether the investment will provide lasting value beyond the tournament.
Uganda has previously invested in sports facilities whose maintenance and commercial utilisation have remained challenges. Namboole itself has undergone repeated refurbishment, making its long-term sustainability an important issue.

In an October 2026 analysis, Daily Monitor highlighted the need for a commercial strategy that would enable Namboole to generate revenue through sporting events, concerts, conferences and other activities after AFCON.
This raises a legitimate question about whether government has developed a clear maintenance and revenue-generation plan for the facilities being constructed and renovated.
The country should not invest hundreds of billions of shillings in infrastructure that becomes expensive to maintain or falls into disuse once the tournament ends.
Ultimately, Uganda’s AFCON 2027 preparations should be judged not only by the appearance of completed stadiums but also by the transparency of the expenditure, the quality of construction and the long-term benefits to the public.
The Ministry of Education and Sports, National Council of Sports, UPDF Engineering Brigade and other implementing agencies must demonstrate how much money was allocated, released, committed and actually spent on each project.
Parliament, the Auditor General and PPDA also have an important oversight responsibility to establish whether the projects are being delivered within their approved budgets, timelines and contractual specifications.
As the countdown to AFCON continues, Ugandans deserve answers to a straightforward question: Are the stadiums being built and renovated delivering value for the billions of shillings invested in them?
The success of Uganda’s AFCON preparations should not end with the final whistle of the tournament. It should be measured by whether the country emerges with quality, sustainable sports infrastructure that serves generations of Ugandans.

Tags: #AfCON2027Africa cup of NationsAkibua stadiumNambole stadium

Related Posts

Health

Rooney reveals he contemplated suicide during Manchester United career

November 17, 2026
Manchester United pursue Pochettino as Palace dismiss Sage
Sports

Manchester United pursue Pochettino as Palace dismiss Sage

November 12, 2026
Sports

Manchester Fires Michael Carrick Oops

November 12, 2026
Namuwongo Blazers to host Road to BAL tournament in Hoima
Sports

Namuwongo Blazers to host Road to BAL tournament in Hoima

October 16, 2026
Uganda Set to Host Rugby Africa Men’s 7s
Sports

Uganda Set to Host Rugby Africa Men’s 7s

September 21, 2026
Mbarara City Storms to Group C Top Position
Sports

Mbarara City Storms to Group C Top Position

June 27, 2026
Please login to join discussion

POPULAR NEWS

Catholic Priest Dies During Holy Mass

Catholic Priest Dies During Holy Mass

February 6, 2026
Men Sucking Women’s Breasts Doesn’t Prevent Cancer, Oncologists

Men Sucking Women’s Breasts Doesn’t Prevent Cancer, Oncologists

October 17, 2025
Minister Amongi, Akena Scrapped from EC Voters’ Register Oops

Minister Amongi, Akena Scrapped from EC Voters’ Register Oops

September 3, 2025
Bubangizi SS Student Dies Hours to UACE Exams

Bubangizi SS Student Dies Hours to UACE Exams

November 9, 2025
Catholic Priest Speaks Out Against Museveni and Son’s Leadership

Catholic Priest Speaks Out Against Museveni and Son’s Leadership

February 16, 2025

EDITOR'S PICK

Police: Hilux Driver Lost Control in Fatal Entebbe Crash

Police: Hilux Driver Lost Control in Fatal Entebbe Crash

August 7, 2026

Museveni Pardons Ex NSSF Boss

January 18, 2024

29M Ugandans use mobile phones, 22M subscribe to internet

September 15, 2021

Haiti struck by deadly 7.2-magnitude earthquake

August 15, 2021
VINAStech advert VINAStech advert VINAStech advert
ADVERTISEMENT

About

Parrots Media

A Public Relations and Media Services Company registered and licensed to operate in Uganda and the Great Lakes Region.

Follow us

Categories

  • Business
  • BUSINESS REPORTS
  • CLIMATE ACTION REPORTS
  • Climate Change
  • COMMUNITY REPORTS
  • Education
  • Entertainment
  • FEATURES
  • Health
  • Lifestyle
  • News
  • News
  • Obituary
  • OBITUARY
  • Opinions
  • RELIGION
  • Religion
  • Science and Technology
  • Sports
  • Sports and Entertainment
  • TOURISM

Recent Updates

  • Do Uganda’s Stadium Projects Reflect the Billions Invested?
  • British-Ugandan returns to Entebbe childhood home after nearly 60 years
  • Mao admits JLOS credibility at stake as Uganda prepares for Justice Week
  • Museveni, Samia Hold Talks at State House Entebbe, Agree to Fast-Track EACOP and SGR
November 2026
M T W T F S S
 1
2345678
9101112131415
16171819202122
23242526272829
30  
« Oct    
  • About Us
  • Internship
  • Contact Us

© 2025 Parrots Media | Website Designed and Maintained by VINAStech

No Result
View All Result
  • Parrots Media
  • News
  • Business
  • Science and Technology
  • Sports and Entertainment
  • Lifestyle
  • Others
    • Climate Change
    • Education
    • Religion
    • Opinions

© 2025 Parrots Media | Website Designed and Maintained by VINAStech

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

You cannot copy content of this page